Truck Route Schedules
MWI Components, headquartered in Spencer, Iowa, efficiently serves the Midwest and Northeast United States through a network of dedicated truck routes, ensuring timely delivery of their post-frame building products. Their logistics system includes several specialized routes, each with specific loading and delivery schedules.
Please note that Holidays will affect our Truck Route Schedules.

Bullseye Route
Weekly Route
Loads: Tuesdays
Delivery: Wednesdays - Fridays

Triad Route
Weekly Route
Loads: Mondays
Delivery: Tuesdays - Fridays

Spade Route
Monthly Route
Loads: 1st & 3rd Mondays
Delivery: 1st & 3rd Tuesdays - Fridays

Diamond Route
Weekly Route
Loads: Mondays
Delivery: Tuesdays - Fridays

Star Route
Weekly Route
Loads: Wednesdays
Delivery: Thursdays- Fridays

Clover Route
Weekly Route
Loads: Fridays
Delivery: Following Mondays - Fridays

Cube Route
Monthly Route
Loads: 2nd & 4th Fridays
Delivery: 1st & 3rd Week of the Month

Infinity Route
Monthly Route
Loads: 1st & 3rd Fridays
Delivery: 2nd & 4th Week of the Month
Lead Times
Order Due Date Formula
Order Due Date = Load Date − Lead Time (in full business days)
Examples:
-
Hardware (Triad Route)
-
Load Date: Monday, April 22
-
Lead Time: 7 business days
-
Order Due Date: Monday, April 15
-
-
Horse Stalls (Triad Route)
-
Load Date: Monday, April 22
-
Lead Time: 10 business days
-
Order Due Date: Monday, April 8
-
At MWI Components, we carefully calculate our lead times to ensure every order is delivered promptly and efficiently, based on the specific product and the truck route it’s scheduled for. We’ve built our reputation on speed and reliability, and we take great pride in offering what we believe are the fastest lead times in the industry. Our team understands how critical timing is to our customers' projects, which is why we’ve designed our scheduling system to be clear, dependable, and responsive to each product’s manufacturing needs.